When a depot charger fails, the immediate operating question is which vehicles can still leave with the energy their work requires. Restoring equipment matters, but dispatch cannot wait for a repair estimate alone. Use a reduced-service plan that connects the available charging positions to the next departure schedule.

The plan should be prepared before a fault, then updated with the real conditions of the incident. It must not depend on every vehicle having the same energy need or every working connector being suitable for every vehicle.

Establish what service remains available

Identify the failed equipment and any restrictions affecting neighbouring outputs or shared systems. Ask the operator or service team to confirm the usable charging positions and power allocation. Count vehicles that can actually charge at the same time, rather than the cables still visible in the depot.

Check vehicle compatibility and access to those positions. A working charger behind a blocked vehicle, or one unsuitable for the required vehicle, does not provide an immediate recovery route.

BENY's commercial AC and DC charging families cover different equipment types. A depot contingency plan should use the actual installed configurations and their available support arrangements, not assume that another family or an unverified spare can replace the failed service.

Prioritise the work, not the fullest battery

Create a departure list showing the vehicle, planned departure time, essential energy requirement and available starting information. Where state of charge is unknown or unreliable, keep that uncertainty visible and use the fleet's approved process to resolve it.

Give priority according to an agreed operational rule. An early essential route may take precedence over a later optional journey. Charging every vehicle to the same target percentage can waste scarce access if different routes need different amounts of energy.

Have dispatch approve changes to the service plan. The charging operator should not quietly reduce a vehicle's energy target without the team responsible for that vehicle's work understanding the consequence.

Check whether the reduced plan can fit

Use a simple energy-and-time calculation as an initial screening step, then verify the actual vehicle and equipment constraints. Energy required divided by available time gives an average delivery requirement; it does not prove that a charging session can sustain that rate.

For example, suppose three vehicles need an additional 45, 20 and 10 kWh at their batteries before departure: 75 kWh in total. If the surviving charger can supply at most 40 kW during a common two-hour window, 80 kWh is only a theoretical output at the charger boundary. It is not a dependable 5 kWh margin over the vehicles' needs. Connection changes, allocation, vehicle acceptance, losses between those boundaries and interruptions still need consideration.

The example shows why a plan that only just fits a nameplate calculation deserves further review. Identify the first departure at risk and the latest time at which a different operating decision must be made.

Agree alternatives before the decision deadline

Possible responses include reassigning a suitable charged vehicle, changing the route schedule or using an approved external charging option. Check the operational, access and vehicle constraints for the actual alternative rather than listing it as guaranteed recovery capacity.

If the plan requires moving vehicles during the night, name the person authorised and available to do it. If it relies on a third-party site, verify practical access and the fleet's payment arrangements. A location on a map is not a confirmed charging reservation.

Keep electrical repairs and work on charging equipment with authorised personnel. Dispatch urgency does not make improvised connections or repeated fault resets an acceptable operating plan.

Maintain one incident and dispatch record

Record the fault, usable capacity, revised vehicle order, changes approved by dispatch and the next review time. Keep the service ticket reference so operational decisions can be connected to the repair timeline.

When the equipment returns, confirm its accepted status with the responsible team before putting it back into the schedule. Update affected staff and remove temporary arrangements deliberately.

Afterwards, review which commitments were missed and why. That evidence can justify a spare-parts arrangement, a different service response or additional charging resilience. It is more useful than treating every charger outage as the same event, because it shows the specific gap between the remaining infrastructure and the depot's next required departures.